Spectators lined the shores of Hobart's River Derwent on Friday to witness a rare maritime spectacle: the loading of the world's largest battery-equipped, electric-powered ferry onto a heavy-lift transporter ship. The operation, which involved the MV Black Marlin semi-submerging to receive the ferry Hull 096, was described by onlookers and officials as one of the most complex marine undertakings in Tasmania's history.
Coverage comparison
ABC Australia reported the event as a multi-day operation that drew crowds to Tranmere and other vantage points. The broadcaster's coverage highlighted both the technical complexity and the community's fascination with the slow-moving process. Earlier reports from the same outlet had previewed the operation as a "rare sight" for Hobart, emphasizing the ship's arrival from South Africa and the challenges leading up to the loading.
Key claims
The MV Black Marlin, one of the world's largest heavy-lift ships, completed its journey from South Africa and anchored 1.5 kilometres off Tranmere on Hobart's eastern shore. The vessel, which is Dutch-operated, measures 217 metres in length and 42 metres in width, making it one of the biggest ships to enter the River Derwent.
The ship was in Hobart to pick up the battery-electric powered ferry Hull 096, built by Hobart shipbuilders Incat for South American ferry company Buquebus. The ferry, which can transport up to 2,100 passengers, will be officially named China Zorrilla after the Uruguayan actress. It is set to service the Rio de la Plata route between Colonia del Sacramento in Uruguay and Buenos Aires in Argentina.
The loading operation was originally scheduled for April, but faced delays when the initial heavy-lift vessel booked to transport the ferry became stuck in the Persian Gulf due to the US-Iran conflict. According to Incat chairman Robert Clifford, the first ship is still stuck in the Persian Gulf, and the company had to secure the Black Marlin in June as a replacement. Clifford described the waiting period as "challenging" but said the company was looking forward to the loading process.
The operation, which involved dozens of people and took several days, concluded on Friday with the successful loading of Hull 096 onto the Black Marlin's submerged deck. An exclusion zone of 500 metres was in place during the operation. The process was "unlike anything that had ever taken place in Tasmanian waters," according to ABC Australia's reporting, which noted that the loading was one of the most significant maritime operations ever undertaken in Tasmania.
The Black Marlin is expected to depart on Monday for a 40-day voyage to South America. Incat is also building three other, slightly smaller battery-powered electric ferries.
Perspectives
Incat chairman Robert Clifford acknowledged the challenges of the delayed transport, telling ABC Australia: "It's been a challenging two or three months, waiting for the ship to arrive. We're now looking forward to the process of getting the ferry onto the ship."